ISEB Software Testing Intermediate 認定 ISEBSWTINT_001 試験問題:
1. Which two of the following measures would give the best indication of likely product quality?
a. Number of hours of overtime worked.
b.Number of test runs.
c.Coverage of requirements achieved.
d.Defect trends. e.Budget sent so far.
A) c and d.
B) d and e.
C) b and d.
D) a and c.
2. Which of the following are product risks and which are project risks?
a.The navigation through some parts of the website may need to be different from others.
b.Sprint 1 may not be completed on time, leading to a delay to the start of Sprint 2.
c.Text versions of images may not always be possible.
d.There may be a need to buy a capture-replay tool for regression testing.
e.A key member of the team may leave before the Sprints have been completed.
A) a and c are products risks, b, d and e are project risks.
B) b, c and e are product risks, a and d are project risks.
C) a, d and e are product risks, b and c are project risks.
D) a, b and c are product risks, d and e are project risks.
質問と回答:
質問 # 1 正解: A | 質問 # 2 正解: A |