SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 認定 C-TSCM42-64 試験問題:
1. When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure would you use to process the problem in order to create a solution that is feasible from a requirements planning perspective?
A) Total planning online
B) Multi-level single-item planning with the display results before saving option
C) Interactive single-item planning for the delayed assembly
D) Multi-level single-item planning with the simulation mode option
2. With which functions of the process order can you fulfill the requirements of the Good Manufacturing Practices (GMP) standard? (Choose three.)
A) Digital signature
B) Material identification and reconciliation
C) Batch record
D) Availability check
E) Resource selection
3. Which of the following prerequisites have to be fulfilled for production orders to be transferred to a business data entry system via the Plant data collection (PP-PDC) interface? (Choose three.)
A) Production orders contain at least one operation that contains a work center with a subsystem group assigned to it.
B) Execution Steps were used to record process instructions in the operation.
C) The application of the PP-PDC interface was activated in the order type for the production order.
D) Production orders have been released.
E) The material to be produced with a production order was flagged for transfer in its material master.
4. In SAP ECC, you calculate the standard available capacity for a work center capacity with the following data: start: 7:00:00 a.m., end. 3:00:00 p.m., break duration: 1 hour, rate of utilization: 80%, overload. 110%, number of individual capacities: 1.
How large is the standard available capacity?
A) 7 hours
B) 8 hours
C) 5.6 hours
D) 6.16 hours
5. Which information is contained in production versions for selecting routings and bills of material?
A) The routing and BOM alternatives to be used for production
B) The explosion date on which the validity of the routing and bill of material is checked
C) The plant for which the routing and BOM have to be created
D) All the control parameters for selecting routings and bills of material
質問と回答:
| 質問 # 1 正解: D | 質問 # 2 正解: A、B、C | 質問 # 3 正解: A、C、D | 質問 # 4 正解: C | 質問 # 5 正解: A |














966 お客様のコメント
品質保証JPexamはIT認定試験のシラバスに従って、試験問題の範囲を正確に絞って、的中率が99%の最新問題集を捧げます。
1年間の無料更新サービスJPexamは1年以内に問題集の無料更新サービスを提供し、お客様がいつでも最新版の問題集を持つことを保証いたします。もし試験の内容が変更されたら、弊社は直ちにお客様にお知らせします。それに、弊社の問題集が更新されたら、早速メールで最新バージョンを送付いたします。
全額返金JPexamの問題集を利用すると、短時間で勉強しても試験に合格できるのを保証いたします。試験に不合格になってしまった場合、弊社は全額返金いたします。(
ご購入前のお試しJPexamは問題集のサンプルを無料で提供いたします。ご購入前にサンプルを試用して製品の品質を確認することができます。ご遠慮なく利用してください。