Oracle EBS R12: Advanced Supply Chain Planning 認定 1Z0-244 試験問題:
1. With reference to Resource Batching, the planning engine did not find enough order quantity within the batching window to at least meet Minimum Batch Capacity.
Identify two actions that the planning engine performs in the above situation.
A) issues an exception message
B) starts a batch with less than the minimum quantity
C) applies penalty factors if the resource is of type "Machine"
D) determines minimum and maximum batch sizes
E) starts a batch with more than minimum quantity
F) constrains resources along multiple dimensions
2. Identify the five Resource types that can be defined In Oracle.
A) Currency
B) Amount
C) Lead Time
D) Person
E) Bill of Material
F) Item
G) Machine
H) Miscellaneous
3. Identify four exception messages that are most likely to appear In an unconstrained plan.
A) Orders with compression days
B) Supplier Capacity overloaded
C) Planned Order uses alternate DIM of Material/Routing
D) Order with Insufficient lead time
E) Items with a shortage
F) Resource overloaded
G) Order lead time constraint
4. In Oracle ASCP, which three types of plan can be launched?
A) Production Plan
B) Manufacturing Plan
C) Material Constrained
D) Resource Constrained
E) Master Plan
F) Reorder Point Plan
G) Mln-Max Plan
5. You are Integrating Oracle Distribution Planning with other Oracle Advanced Planning Suite products.
To which Oracle Advanced Planning Suite product does Distribution Planning provide a statement of product availability?
A) Oracle Demand Planning
B) Oracle Collaborative Planning
C) Oracle Global Order Promising
D) Oracle Inventory Optimization
E) Oracle Advanced Supply Chain Planning
F) Oracle Production Scheduling
質問と回答:
質問 # 1 正解: A、E | 質問 # 2 正解: A、B、D、G、H | 質問 # 3 正解: A、C、E、G | 質問 # 4 正解: A、B、E | 質問 # 5 正解: C |